Initial planning session with the MAD team - if all goes well, a ES, CP and BP should be delivered in this iteration from the development side - however, the time frame does not allow for adequate testing before the end of the iteration.

Summary of discussion points


  • AA to follow up (later next week?) with how the heck are we going to  test of the CT
  •  DKto investigate / add a task for the Get Locality ES
  •  I’ve already spoken to DM regarding scope and learning curve for this iteration
  • The Bug fixing tasks have 0 hours estimated – I will follow this up with AW / DW and the BA’s to determine a good way of estimating this task.
  • MJ raised concerns regarding the development of the CT transactions at the end of the process, as opposed to in conjunction – this probably needs to be followed up with the developers (MJ?)